There are quite a few outputs from Closing a Project necessary to enable a controlled close down of the PRINCE2 project:
- Customer acceptance of the project's deliverables
- Operational and Maintenance acceptance of responsibility for the deliverables
- a Project Closure recommendation to the Project Board
- Recommendations for follow-on actions, perhaps to clear up any 'pending' issues that were not delat with during the project
- a post-project review plan, setting out how benefits will be reviewed
- a lessons learned report
- an End Project Report of the performance of the project against its Project Initiation Document.
When the Project Board is happy with this lot, then they can confirm project closure.